Construction and Building Materials Use Tax Collection. The collection of the use tax for construction and building materials will be administered at the direction of the Board of County Commissioners. The Use Tax may be paid by estimate through the payment of the tax at the time permits are issued for building and construction. As an alternative to the estimate procedure provided above, payment of this use tax may be made by the filing by any applicant for a building permit of an affidavit stating that the applicant intends to purchase all building and construction materials necessary for the project described in the building permit application from a licensed retailer licensed within the County. Every building permit applicant who utilizes the alternative procedure provided above shall maintain and preserve detailed purchase and receipt records which shall be subject to inspection and audit by employees of the Board of County Commissioners, and any unpaid taxes due shall be subject to collection. The collection and administration of the use tax imposed by this Resolution shall be performed at the direction of the Board of County Commissioners in substantially the same manner as the collection, administration and enforcement of the Sales and Use Tax of the State of Colorado.
Collection Prior to April 1st, 2009. When the voters of El Paso County first approved the 1% Sales and Use Tax the Board of County Commissioners enter into an Intergovernmental Agreements (IGA) with the City of Colorado Springs to administer and Collect Use Tax on the behalf of El Paso County. The City of Colorado Springs will continue to collect use tax on all permits issued before April 1st 2009.
Collection On or After April 1st, 2009. On November 20th, 2008 the Board of County Commissioners approved Resolution 08-481 which changes the point of use tax collection from the City of Colorado Springs to the Pikes Peak Regional Building Commission (PPRBC) via an Intergovernmental Agreement. The new collection procedures will take affect on April 1, 2009
The following written information is a general overview of the Use Tax collection system. To view the Resolution in its entirety please follow the links below:
Resolution 08-481 and Intergovernmental Agreement.
Use Tax Exemption
When the permit applicant believes a project is exempt from Sales and Use Tax, the applicant must submit a Colorado Certificate of Exemption and a completed Use Tax Exemption Request Form to El Paso County for approval prior to issuance of the building permit.
27 East Vermijo Avenue
Colorado Springs Colorado
80903-2208
Phone: 719-520-6400
Fax: 719-520-6486
Email: usetax@elpasoco.com
*Response is quicker via email
The Use Tax Collection System
Whenever a building permit is issued for construction related work within the jurisdiction of the Regional Building Department, the permit applicant shall choose one of following methods offered to ensure the payment of the El Paso County Use Tax. The three methods are as follows:
· Job Material Valuation Method
· Actual Cost Method
· Affidavit Method
- A permit applicant who selects to pay Use Tax by the job material valuation method can choose to submit 100% of the estimated Use Tax or deposit 50% of the estimated Use Tax with the Regional Building Department when the permit is issued. If the Permit owner chooses to deposit 50% of the estimated Use Tax, the remaining balance is collected as a condition for the issuance of the Certificate of Occupancy or final inspection, whichever occurs later. 40% of the total construction cost is the estimated value of materials used in determining Use Tax owed. The permit receipt shall serve as the Exemption Certificate for use when purchasing building and construction materials.
Note: The permit owner is responsible for insuring subcontractors receive a copy of the permit receipt for use when purchasing building and construction materials.
EXAMPLE:
|
Total building valuation |
$180,000.00 |
|
40% of $180,000 = |
$ 72,000.00 (estimated material cost) |
|
$72,000 at 1% = |
$ 720.00 amount added to permit fee |
In the above example, half of the $720.00 ($360.00) shall be deposited along with the applicable administrative fee and the permit will be issued. The remaining balance must be submitted prior to the Certificate of Occupancy or final inspection, which ever is later.
When the permit owner believes the material cost for the project is less than the 40% estimated cost using the job material valuation method, the permit owner may submit a Reconciliation Report containing a list of all receipts and contract amounts associated with the project. The Reconciliation Report must be submitted within (180) calendar days of Certificate of Occupancy or final inspection which ever occurs later. El Paso County will provide a written decision within (30) calendar days whether a refund will or will not be issued. During this (30) day period the County may request from the permit owner or subcontractors some or all of the receipts listed on the Reconciliation Report.
- The permit applicant may elect to pay for the Use Tax on the materials used by the actual cost method, which follows the same formula for estimating Use Tax and payment schedule as determined by job material valuation method with the following conditions:
EXAMPLE:
|
Total building valuation |
$180,000.00 |
|
40% of $180,000 = |
$ 72,000.00 (estimated material cost) |
|
$72,000 at 1% = |
$ 720.00 amount added to permit fee |
In the above example, half of the $720.00 ($360.00) shall be deposited along with the applicable administrative fee and the permit will be issued. The remaining balance must be submitted prior to the Certificate of Occupancy or final inspection, which ever is later.
· The permit applicant must declare prior to the issuance of a building permit that they will follow the actual cost method of determining Use Tax due. The permit receipt shall serve as the Exemption Certificate for use when purchasing building and construction materials.
Note: The permit owner is responsible for insuring subcontractors receive a copy of the permit receipt for use when purchasing building and construction materials.
· As a condition of receiving a Certificate of Occupancy or final inspection, the permit owner shall make an appointment for a tax payment reconciliation conference with El Paso County and deposit a payment with Regional Building Department in an amount determined by the job material valuation method. The County personnel assigned this duty shall schedule a meeting no more than sixty (60) calendar days from the date the request is received.
· The customer shall complete and submit a Reconciliation Report containing a list of all receipts and contract amounts associated with the project no more than (30) calendar days from Certificate of Occupancy or final inspection which ever occurs later. The County personnel will request at least (15) calendar days prior to the meeting from the permit owner or subcontractors some or all of the receipts listed on the Reconciliation Report. Failure to provide all requested receipts will disqualify the permit applicant from calculation of Use Tax under this method.
· Adjustments up or down from the Use Tax deposited will be made after the reconciliation is complete.
· If the reconciliation reveals an underpayment of Use Tax, the permit holder will have (30) calendar days from final written reconciliation notice to remit payment without incurring interest or penalties.
- The permit applicant who selects the affidavit method shall sign the affidavit stating that regardless from where construction and building materials are purchased, it is agreed and understood that all applicable County Sales and Use Taxes will be paid by the permit applicant; the applicant shall maintain records demonstrating payment of the applicable Sales and Use Taxes; any construction and building purchased in which El Paso County Sales Tax was not paid is subject to Use Tax which shall be submitted using a separate Consumer Use Tax Remittance form for each permit; and they further agree and understand that they may be subject to an audit of these records.

Program Administration Fee
An administrative fee will be assessed on each permit issued for all construction related work in El Paso County to recover the administrative costs of collection. The following table is a condensed list of the administrative fee schedule used by the Regional Building Department.
|
Codes |
Surcharge |
|
101/102-New Residential |
$10.00 |
|
112/1121-Mobile Homes |
$4.00 |
|
100-300-New Commercial |
$50.00 |
|
New Commercial MEP |
$5.00 |
|
3292-New Signs |
$4.00 |
|
434/436-Residential Remodel |
$4.00 |
|
437-Commercial Alterations |
$20.00 |
|
437-MEP |
$5.00 |
Complete surcharge schedule:
http://adm.epc.com/NR/rdonlyres/1780DD26-6111-4F68-A4BF-C2384966C019/0/AdministrativeFeeSchedule.pdf
All projects are subject to Audit
All related construction records are subject to audit by the County following project completion. Such audit is designed to determine the actual taxable cost of the project and may be conducted any time within 18 months after the Certificate of Occupancy or final inspection, whichever occurs later. The audit will reconcile the Use Tax deposit paid against the actual tax due on the materials. It is important that you keep complete and accurate records of each project. A copy of the contract including change orders, all invoices, receipts and cost reports pertaining to the construction project shall be kept for at least eighteen (36) months after the certificate of occupancy or final inspection, whichever occurs later.
If a formal audit by the County reveals an underpayment of the Use Tax, the remainder of the unpaid Use Tax, along with any interest and penalties will be assessed to the permit applicant.
A complete audit is performed by the County on all refund requests initiated by the contractor.
Penalty Interest For Underpayment of Use Tax
The interest and penalty interest rate for underpayment of the due and owing Use Tax (“Underpayment”) regardless of the method of payment chosen by the customer will pay to the County the amount of the underpayment shall be the same as allowed under Section 39-26-207, C.R.S., 2008, as amended. The amount of interest shall accrue from the date due, which is the date Certificate of Occupancy is issued or final inspection, whichever occurs later, and shall continue to accrue until paid. Upon written notification by the County of the amount of the underpayment, the customer may immediately pay the amount of the underpayment to stop interest from accruing while an appeal is undertaken.
If you wish to review the Agreement in its entirety, please follow the link below.
Intergovernmental Agreement.